GYMSHARK LIFTING CLUB
COMPLETE SOLUTION
GSLC was the second property added to their portfolio, a 60,000 sq ft warehouse unit. Gymshark wanted a multipurpose space as an "extension' to their current HQ. GSLC launched in August 2019.
SERVICES
Reporting into Gymshark Executive Chairman
Complete Property and FM management Model used as outlined in my services page, as requested by the client.
Design and build project
£6 million fit out budget
£350,000 Annual FM budget
Multi purpose space - 60,000sq ft
GSLC - Fully equipped lifting
club staff gym
Creative hub - E-comm studios
Soundproof App studio
Agile office space
Innovation hub
OUTCOMES
Landlord liaison on behalf of client throughout project.
Management of D&B company to deliver to scope, timeline and budget.
Budget and cost management for build and FM services.
Supported the site FM in tendered, selection and mobilisation of FM services and contracts.
Project was brought in on time and to projected budget.